Quick answer
A low-risk Open CTI migration has six phases: assess, configure, map call flows and reports, test and pilot, cut over, then train and provide hypercare. Salesforce’s sample plan is about eight weeks, which is a rough scale, not a guarantee. Number porting can take several weeks, so start early and keep a rollback plan.
A Step-by-Step Open CTI Migration Plan: Phases, Timeline, Risks, and Cutover
A telephony change touches agents, customers, and reporting at the same time, so an Open CTI migration should not be treated as a weekend adapter swap. Salesforce has set Open CTI end of life for February 28, 2028, and already blocked it on newly created Agentforce Service orgs. The teams that finish calmly inventory early, rebuild flows in a sandbox, pilot with a fallback, and only then cut over.
This is the phased plan Rajesh Rathod IT Solutions uses to move Salesforce teams to Vonage Contact Center (VCC), powered by AI. It aligns with Salesforce’s public migration guidance — the Trailhead sample timeline and the developer checklist for Partner Telephony — and adds the carrier, porting, training, and hypercare work a live contact center needs. Check your org’s Salesforce notices as well, because some instructions can be org-specific.
How long does it take?
There is no honest one-size answer. Open CTI migration services with us are a fixed fee, scoped after a free assessment, with an itemized quote and a confirmed timeline before work starts. Salesforce Trailhead publishes a sample plan of about eight weeks from inventory through decommissioning the Open CTI package. Treat that as a rough scale, not a guarantee. Number porting can take several weeks on top of configuration — Salesforce Help notes two to four weeks depending on the carrier, and multi-country inventories can take longer. Custom adapter logic, many queues, or heavily customized reports also extend the work. Starting early keeps the plan phased, instead of compressed against February 28, 2028.
| Salesforce sample week | Activity (from Trailhead) | How we map it in a Vonage migration |
|---|---|---|
| Week 0 | Complete the inventory: users, phone numbers, existing reports, and custom logic. | Assessment: audit the Open CTI adapter, users, queues, screen pops, click-to-dial, routing, custom code, and call-data reports. |
| Weeks 1–2 | Install the managed package or turn on Voice; set up the Contact Center, Omni-Channel, service channels, queues, and presence. | Configuration: provision Vonage Contact Center and the Vonage package for Salesforce Voice; design Omni-Channel for voice; assign licenses and permission sets. |
| Week 3 | Build the Omni-Channel flow for screen pop, and a record-triggered flow on VoiceCall if needed. | Data and call-flow mapping: rebuild IVRs, queues, screen pops, and automations against the Voice Call record. |
| Week 4 | Sandbox validation with selected reps on real or simulated calls. | End-to-end sandbox testing before any live traffic moves. |
| Week 5 | Parallel run: keep Open CTI live while a separate rep group runs Voice with real call volume. | Pilot on a live queue, with the legacy adapter kept as a fallback. Reps can belong to only one contact center at a time, so the pilot group is a separate set of people. |
| Week 6 | Production cutover, ideally midweek and midmonth. | Phased go-live by team or queue, with a documented rollback plan. |
| Weeks 7–8 | Post-go-live monitoring, phone number porting, then decommission Open CTI after verification. | Training, hypercare, porting completion, reporting tune-up, and only then retirement of the legacy adapter. |
The six-step plan we use
1. Assessment
Start with a complete picture of what Open CTI is doing today. In this phase we:
- Audit the current Open CTI adapter, assigned users, and queues.
- Inventory screen pops, click-to-dial, routing rules, custom code, reports, and dashboards that depend on call data.
- List every number in use: direct lines, queue numbers, and toll-free numbers, including any numbers that must be ported.
- Map each important Open CTI behavior to a Salesforce Voice equivalent. Salesforce’s developer guide also recommends auditing
opencti.*calls, custom fields on CTI-created Tasks, and any external system calls from the adapter.
This is also when we confirm whether Vonage Contact Center (VCC) is the right path, or whether a Salesforce-native contact center is a better fit. See the comparison on OpenCTI Migration Help.
2. Configuration
Once the design is agreed, we provision the new stack without changing the live customer experience:
- Provision Vonage Contact Center and the Vonage package for Salesforce Voice.
- Enable and design Omni-Channel for voice, including service channels, queues, routing configurations, and presence statuses.
- Assign licenses and permission sets to reps and supervisors.
- Connect supervisor tools so listen-in and barge-in can be tested later, where those capabilities are in scope.
The legacy adapter stays in place until a later, planned cutover.
3. Data and call-flow mapping
This is the work that prevents “the phone works, but Salesforce does not.”
- Map existing IVRs, queues, and routing to Vonage Contact Center.
- Rebuild screen pops and related logic as Omni-Channel flows in Flow Builder, rather than leaving them in adapter JavaScript.
- Re-point reports, automations, and post-call record creation to the Voice Call record. Salesforce documents Voice Call fields such as call duration, wait time, and disposition as the replacements for many CTI Task metrics.
- Decide which target object a completed call should create or update: Case, Opportunity, Lead, Task, or a custom object.
If you skip this phase, agents may take calls on day one while supervisors lose historical reporting. That risk is common, and it is avoidable.
4. Testing and pilot
We test in two layers.
Sandbox testing comes first: inbound and outbound calls, screen pops, transfers, hold and mute, wrap-up, recordings, and correct Voice Call links. Salesforce’s checklist also includes Command Center for Service (formerly Omni Supervisor) showing the correct rep and call state, post-call record creation, supervisor listen-in and barge-in where required, and a multi-tab test.
A live pilot comes next, on a real queue, with real call volume. Salesforce is clear that a parallel run on simulated calls is not enough, and that a representative can belong to only one contact center at a time, so the pilot group and the Open CTI group must be different people. The legacy adapter stays available as a fallback, and calls can be forwarded from original numbers to temporary numbers if porting is not finished.
5. Cutover
Cutover is phased and scheduled, not a single unplanned flip.
- Move remaining teams or queues in waves, ideally outside peak hours. Salesforce’s sample plan suggests midweek and midmonth, a sensible default when your peak patterns allow it.
- Complete number porting where needed. Vonage provides in-house number porting. We gather account details and Letters of Authorization, validate with the current carrier, and set port dates outside peak hours. Temporary numbers or forwarding can cover the gap.
- Keep a documented rollback plan until the new path is stable.
If you also need cloud phone lines for non-contact-center users, that work can be planned alongside cutover. See business phone lines (USA and international) for Vonage Business Communications.
6. Training and hypercare
- Role-based training for agents, supervisors, and Salesforce admins, including the Omni-Channel voice experience, wrap-up, and the new Voice Call reports.
- Elevated support after go-live while routing, quality, and reporting are tuned.
- Ongoing administration after hypercare: moves, adds, changes, IVR updates, and user onboarding, with escalation into Vonage partner support when needed.
- Only after a verification period do we decommission the Open CTI package, consistent with Salesforce’s sample week 8 guidance.
Risks to plan for, not discover at cutover
- Starting too late. Configuration, flow rebuilds, testing, porting, and training all take time. As the deadline nears, demand for experienced resources will rise.
- Number porting timelines. Porting is regulated and cannot be rushed. Do not make cutover depend on an unscheduled port.
- One contact center per user. A rep cannot sit in Open CTI and Voice at the same time, so the pilot group must be a separate set of people.
- Reporting built on Tasks. If you do not rebuild reports against Voice Call, supervisors lose the metrics they use to run the floor.
- Custom adapter logic left behind. Screen pops and routing that lived in Open CTI JavaScript must be redesigned as Omni-Channel flows.
- Complex IVRs. Large or deeply nested call flows take time to recreate and test in a sandbox before cutover.
- Agentforce expectations. Open CTI blocks full Agentforce activation in the contact center. If AI agents, transcription, or contextual handoff are in scope, they belong in the Voice design.
What we need from you to start
- A short description of your Salesforce org, current telephony vendor, and Open CTI adapter.
- Approximate agent counts, queues, and countries or number ranges in use.
- Any hard dates, peak seasons, or compliance requirements we must plan around.
- Whether Agentforce, unified communications, or additional Vonage solutions are part of the target design.
Salesforce system integrators who already lead the CRM work can bring us in for telephony, porting, and Vonage deployment through the Salesforce SI Partner Program. You keep the client relationship and the Salesforce delivery; we supply, port, deploy, and support Vonage.
Frequently asked questions
How long does an Open CTI migration take?
It depends on your adapter, queues, custom code, reports, and number porting. Salesforce’s sample plan is about eight weeks, and porting can take several weeks. Neither figure is a guarantee. We confirm the timeline in a project plan after a free assessment.
Will customers notice the cutover?
The aim is that they do not. We test in a sandbox, pilot with a separate group on real volume, keep a fallback, schedule cutover and porting outside peak hours, and provide hypercare after go-live.
Can we keep our phone numbers?
Yes. Existing numbers can be ported. Vonage provides in-house number porting. Because porting can take several weeks, we start it early and can use temporary numbers or call forwarding during the transition.
What happens to our call reports?
Most Open CTI reports are built on the Task object. After migration, those reports should be rebuilt against the Voice Call object, which holds richer data such as duration, recordings, and disposition. We inventory reports in assessment and re-point them during mapping.
Is this a fixed-price project?
Open CTI migration services are a fixed fee, scoped after a free assessment, with an itemized quote before work starts. We do not publish a generic price because scope varies.
When should we start, if the deadline is February 28, 2028?
Start the assessment now. The date can look distant, but a careful migration plus porting and training needs slack, and you should be fully off Open CTI well before the deadline. Also check your org’s Salesforce notices. To begin, Book a Free Consultation.
Ready to plan your migration? Book a VCC Demo on Salesforce, or Book a Free Consultation with Rajesh Rathod IT Solutions, a Premier Channel Partner for Vonage. We will assess your setup and return a phased plan and itemized quote.
Sources
- Salesforce Trailhead, “Essential Steps for a Successful Migration Plan,” plan-your-migration.
- Salesforce Developers, “Plan Your Migration” (Open CTI to Salesforce Voice with Partner Telephony), plan-cti-migration.
- Salesforce Developers, “Migrate Reporting,” migrate-reporting.
- Salesforce Help, “Salesforce Open CTI Retirement: End of Life February 28, 2028 – Migrate to Salesforce Voice,” article 005306437.
- Salesforce Help, “Replace Open CTI with Salesforce Voice with Amazon Connect (Path 3),” on porting timelines, cti_migrate_voice_amazon.
- Rajesh Rathod IT Solutions, OpenCTI Migration Help, proposal dated 5 November 2026, and company brochure.